Rehab and Completion of Marisol, Kennedy, Vegas
& Camaselles Sanitary Sewer System
Client’s Name:
The Puerto Rico Aqueducts & Sewer
Authority (PRASA)
Budget: $5,385,609.00
Substantial date: January 18,
2012 (In Progress)
Services: Inspection
Scope:
This project consist in the
Rehabilitation and Completion of the
Marisol, Kennedy, Vegas, and Camaselles
Sanitary Sewer System. The existing
sanitary sewer system was constructed on
two phases, the last one being completed
during 2OO8. The construction of both of
these phases could not be completed due
to difficulties encountered during their
construction. For that reason PRASA
wants to construct this project and
complete the Marisol, Kennedy, Vegas and
Camaselles Sanitary Sewer System.
In summary the project consist of the
installation and replacement of
approximately 6.5 Kilometers of 8”, 12”
and 18” PVC sanitary sewer pipes with
its respective manholes, service
connections and other accessories. With
the exception of some small segments the
installation and replacement of sanitary
sewer pipes will be performed inside the
right-of-way of municipal and state
roads. |
|
|